Tawaheen 450kW Solar Farm

Completion: 
October 2018
Owner: 
Tawaheen Bakery Group
Location: 
Mafraq - Jordan
Scope Summary: 

Survey and substructure ramming works.

Tamam 730kW PV Plant

Completion: 
May 2018
Owner: 
International Poultry Co.
Location: 
Zarqa - Jordan
Scope Summary: 

Survey and Substructure Ramming Works

Invest Bank 730kW PV Plant

Completion: 
May 2018
Owner: 
Invest Bank
Location: 
Um-Rummaneh - Jordan
Scope Summary: 

Survey, PV substructure + inverter room structure ramming

Jaguar 750kW PV Plant

Completion: 
April 2018
Owner: 
Mahmoudia Motors
Location: 
Al-Thuheibeh Al-Gharbia - Jordan
Scope Summary: 

Survey, Substructure Ramming, Structure Assembly, PV Modules Installation

Haddad Factory 350 kW - Zarqa

Completion: 
Scheduled November 2018
Owner: 
Mudieb Haddad & Sons Co.
Location: 
Zarqa - Jordan
Scope Summary: 

Rooftop foundations, and Mechanical works: Structure and PV Module installation.

AJIB 4MW PV Plant

Completion: 
November 2017
Owner: 
Arab Jordan Investment Bank (AJIB)
Location: 
Umm Al-Amad
Scope Summary: 

Setting-out and installation of substructure.